13 September 2017
From Wednesday 13th September contractors are installing steelworks on the North Spine as part of the Spine Remodelling Project.

 

These works will complete on the 21st September in time for the next University Open Day.

To reduce the installation time the site area along the North Spine will widen at various points. This may at times restrict the width of the Spine.

The Spine walkway will be closed between the 19th and 21st of September.

The closure, from the corner of Faraday Building to Subway, will require a diverted route via Faraday main entrance through to Physics Garden. All shops will remain open as usual. The accessible route will be via Bowland Quad, past the Welcome Centre and through the Learning Zone. More details can be found on the attached map.

All business will remain open as usual with the exception of Subway which unfortunately will have to close on Sunday the 16th and Monday the 17th September.

For details of the diversion see the diversion routes section or click here.