LUMS Space programme

The place to realise your ambitions

Lancaster University Management School is embarking on an ambitious infrastructure programme, creating cutting-edge facilities and significantly more space for our students, staff and partners. The School is a place for collaboration; a place where our international community can challenge convention, push boundaries and shape agendas; a place for the very best research-led teaching and engagement.

We’re building the place to be.

Countdown to lift-off: Timeline for building work

7...

Spring 2017

LUMS Lecture Theatres 5-8 move to the Welcome Centre (old Conference Centre)

Bloomberg Room moves to Executive Suite (A217, LUMS)

ISS Technicians from LUMS move to Science and Technology Building (Old Engineering)

6...

Summer 2017

LUMS Reception moves to Meeting Rooms 5 and 6

West Entrance to LUMS (Lancaster Leadership Centre) will relocate to entrance adjacent to Hub Café

Demolition of LUMS Lecture Theatres 5-8

5...

Autumn 2017

Building commences of West and East Pavilions

4...

Spring 2019

Colleagues from 1970s building (including Gillow House) move to Pavilions

3...

Summer 2019

Demolition of 1970s building

Strip out and refurbishment of Gillow House

2...

Autumn 2019

Construction of Hub+ including 2 x 200-seater lecture theatres

Minor refurbishment of existing Leadership Centre 

1...

Spring 2020

Minor refurbishment of Graduate Management School

Lift-off!

Winter 2020

Move into Hub+

Completion of LUMS Space Programme