2 January 2019
Many of you are probably wondering how the new Strength and Conditioning gym and Human Performance Lab are coming on.

As you will have seen, from the outside the shell of the building is basically complete. You will have seen the exterior cladding going on during November and air conditioning units being put in place in the plant room.

Inside the construction, the interior walls are nearing completion and the lighting, cable runs and air conditioning ducting have been installed in the ceiling. The concrete floor has been poured and the interior steel has been coated with fireproof paint.

The project is on schedule and we look forward to the installation of equipment and the opening of the facility in the coming month. 