From mid-February until early May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Graduate College:
House 1 Bassenthwaite - 16 February – late February
House 2 Blea House - 26 February – early March
House 3 Brotherswater - 27 February – mid-March
House 4 Burnmoor - 3 March – late March
House 5 Buttermere - 23 March – early April
House 6 Coniston - 25 March – mid-April
House 7 Crummock Water - 16 March – late March
House 8 Derwentwater - 18 March – late March
House 9 Devoke - 25 March – mid-April
House 10 Elterwater - 9 April – late April
House 11 Ennerdale - 23 April – early May
House 16 Loweswater - 16 February – mid-March
House 21 Ullswater - starting in February until late February
Barker House Farm - 16 March – 7 April
- Scaffolding will be erected or high-level access machinery will be used at one side of each building. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
From Monday 9 – Wednesday 11 February, the Net Zero Energy Project contractor, Vital Energi, will be relaying the paving blocks on East Avenue outside House 5 Buttermere, Alexandra Park.
- The northeast corner of North Avenue outside House 5 Buttermere will be temporarily closed and diversions will be in place.
- Access into Graduate College accommodation will be maintained at all times.
- There will be localised disruption at times.
- Work will progress between 8am - 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at House 20 Thirlmere until the end of February 2026.
- Scaffolding will be erected on one side of the building to enable the contractor to install new pipes to the elevation of the building.
- There will be a temporary footpath closure in the local area. Diversion signage will be in place and all building entrances will be maintained.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at House 24 Winewall and House 27 Crowtrees until the end of February 2026.
- Scaffolding will be erected on one side of the building to enable the contractor to install new pipes to the elevation of the building.
- There will be a temporary footpath closure in the local area. Diversion signage will be in place and all building entrances will be maintained.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at House 19 Stickle until the end of February 2026.
- High-level access machinery will be used on one side of the building to enable the contractor to install new pipes to the elevation of the building.
- There will be a temporary footpath closure in the local area. Diversion signage will be in place and all building entrances will be maintained.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Lonsdale College until the end March 2026:
House 40 Casterton - works have started and will continue until late February 2026
House 43 - Arkholme -works will start 16 February and will continue until end of March 2026
- Scaffolding will be erected or high-level access machinery will be used at one side of each block of houses. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.