From Monday 16 March – early April 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework into the Barker House Farm plantroom.
- On Thursday 26 March, the contractor will drill a core hole into the plantroom to allow the new pipework to be installed. This is in preparation for the final pipework connections.
- Access to the building will be maintained during the work.
- Work will progress between 8am - 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
Until mid-May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Graduate College accommodation. From Friday 6 March until mid-May 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of House 16 Loweswater and House 19 Stickle.
House 1 Bassenthwaite
External pipework installation and insulation: 23 March – late March
Internal mechanical connections: 23 March - late March
House 2 Blea House
External pipework installation: 17 March – mid-March
House 3 Brotherswater
External pipework installation: 17 March – mid-March
House 4 Burnmoor
External pipework installation: 16 March – late March
Internal mechanical connections: 23 March - late March
House 5 Buttermere
External pipework installation: 30 March – early April
Internal mechanical connections: 30 March - early April
House 6 Coniston
External pipework installation: 7 April – mid-April
Internal mechanical connections: 7 April - early April
House 7 Crummock Water
External pipework installation: 27 April – late April
House 8 Derwentwater
External pipework installation: 5 May – early May
Internal mechanical connections: 6 May- early May
House 9 Devoke
External pipework installation: 5 May – mid-May
Internal mechanical connections: 6 May- mid-May
House 10 Elterwater
External pipework installation: 13 April – mid-April
Internal mechanical connections: 13 April - mid-April
House 11 Ennerdale
External pipework installation: 20 April – late April
Internal mechanical connections: 20 April - late April
House 16 Loweswater
External pipework installation: 16 February – end-March
Internal plantroom connections: 27 March – mid-April
House 19 Stickle
Internal plantroom connections: 7 April - 19 May
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Cartmel College accommodation
Until the end of May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Cartmel College accommodation. From Friday 20 March until June 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of the houses.
House 20 Thirlmere
Internal plantroom connections: 6 May – 17 June
House 46 Bigland
External pipework installation: 16 March – mid-April
Internal plantroom connections: 7 April – end April
House 52 Haverthwaite
External pipework installation: 30 March – end April
Internal plantroom connections: 14 April – end April
House 54 Grange
External pipework installation: 15 April – mid-May
Internal plantroom connections: 20 April – early May
House 55 Braystones Tarn
External pipework installation: 2 March – early April
Internal plantroom connections: 20 March – early April
- Scaffolding will be erected or high-level access machinery will be used at one side of each building. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
Cartmel Family Flats and Houses
From 9 April until the end of May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the external district heating pipework to Graduate College - Cartmel Family flats and houses. Vital Energi contractors will be installing external pipework only at this time, in readiness for summer internal connections.
Houses 158 – 162 Lyth: 9 April – early May
Houses 163 -168 Backbarrow: 9 April – early May
Houses 169 -171 Hayeswater: 30 April – mid-May
Houses 172 –179 Seathwaite: 30 April – end May
Encasement work to risers (All spaces): 8 May - early May
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact residents, the University Project Manager will be in contact.
- Dates can be subject to change.
Until mid March 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Pendle College accommodation. From Friday 13 March until mid-April 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of the houses.
House 21 Ullswater
External pipework installation: starting in February – mid-March
Internal pipework connections: 13 March – end of March
House 24 Winewall
Internal plantroom connections: 13 March – end of March
House 27 Crowtrees
Internal plantroom connections: 27 March – mid-April
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Until the end of March 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Lonsdale College accommodation. From Monday 2 March until July 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of the houses.
House 34 Whittington
Internal plantroom connections: 2 March – mid-March
House 36 Tunstall
Internal plantroom connections: 13 May - early July
House 39 Barbon
Internal plantroom connections: 2 March – mid-March
House 40 Casterton
Internal plantroom connections: 20 March – early April
House 43 Arkholme
External pipework installation: 16 February – end of March 2026
Internal plantroom connections: 7 April – end of April
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works, Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.