Until early May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Graduate College accommodation. From Friday 6 March until mid-April 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of House 16 Loweswater and House 19 Stickle.
House 1 Bassenthwaite
External pipework installation: 16 February – late February
House 2 Blea House
External pipework installation: 26 February – early March
House 3 Brotherswater
External pipework installation: 27 February – mid-March
House 4 Burnmoor
External pipework installation: 3 March – late March
House 5 Buttermere
External pipework installation: 23 March – early April
House 6 Coniston
External pipework installation: 25 March – mid-April
House 7 Crummock Water
External pipework installation: 16 March – late March
House 8 Derwentwater
External pipework installation: 18 March – late March
House 9 Devoke
External pipework installation: 25 March – mid-April
House 10 Elterwater
External pipework installation: 9 April – late April
House 11 Ennerdale
External pipework installation: 23 April – early May
House 16 Loweswater
External pipework installation: 16 February – mid-March
Internal plantroom connections: 27 March – mid-April
House 19 Stickle
External pipework installation: 12 January – end of February
Internal plantroom connections: 6 March – end of March
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works from Friday 6 March until mid-April 2026, Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Until early April 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Cartmel College. From Friday 20 March until early May 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of the houses and at Barker House Farm.
House 20 Thirlmere
External pipework installation: 12 January - end of February
Internal plantroom connections: 20 March – early April
House 46 Bigland
Internal plantroom connections: 7 April – end of April
House 52 Haverthwaite
Internal plantroom connections: 14 April – end of April
House 54 Grange
Internal plantroom connections: 20 April – early May
House 55 Braystones Tarn
Internal plantroom connections: 20 March – early April
Barker House Farm
External pipework installation: 16 March – early April
Internal plantroom connections: 27 March – mid April
- Scaffolding will be erected or high-level access machinery will be used at one side of each building. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works from Friday 20 March until early May 2026, Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Until the end of February 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Pendle College accommodation. From Friday 13 March until mid-April 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of the houses.
House 21 Ullswater
External pipework installation: starting in February - end of February
Internal pipework connections: 13 March – end of March
House 24 Winewall
External pipework installation: 12 January - end of February
Internal plantroom connections: 13 March – end of March
House 27 Crowtrees
External pipework installation: 12 January - end of February
Internal plantroom connections: 27 March – mid-April
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works from Friday 13 March until mid-April 2026, Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
Until the end of March 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Lonsdale College accommodation. From Monday 2 March until the end of April 2026, the contractor will then be working on the connection of the external pipework into plantrooms on the top floor of the houses.
House 34 Whittington
Internal plantroom connections: 2 March – mid-March
House 36 Tunstall
Internal plantroom connections: 2March – mid-March
House 39 Barbon
Internal plantroom connections: 2 March – mid-March
House 40 Casterton
External pipework installation: works have started and will continue until late February 2026
Internal plantroom connections: 20 March – early April
House 43 Arkholme
External pipework installation: works will start 16 February and will continue until end of March 2026
Internal plantroom connections: 7 April – end of April
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- For the plantroom connection works from Monday 2 March until the end of April 2026, Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.