From mid-February until early May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Graduate College accommodation:
House 1 Bassenthwaite - 16 February – late February
House 2 Blea House - 26 February – early March
House 3 Brotherswater - 27 February – mid-March
House 4 Burnmoor - 3 March – late March
House 5 Buttermere - 23 March – early April
House 6 Coniston - 25 March – mid-April
House 7 Crummock Water - 16 March – late March
House 8 Derwentwater - 18 March – late March
House 9 Devoke - 25 March – mid-April
House 10 Elterwater - 9 April – late April
House 11 Ennerdale - 23 April – early May
House 16 Loweswater - 16 February – mid-March
House 19 Stickle - 12 January – end of February
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
From Monday 9 – Wednesday 11 February, the Net Zero Energy Project contractor, Vital Energi, will be relaying the paving blocks on East Avenue outside House 5 Buttermere, Alexandra Park.
- The northeast corner of North Avenue outside House 5 Buttermere will be temporarily closed and diversions will be in place.
- Access into Graduate College accommodation will be maintained at all times.
- There will be localised disruption at times.
- Work will progress between 8am - 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Cartmel College:
House 20 Thirlmere 12 January - end of February
Barker House Farm - 16 March – 7 April
- Scaffolding will be erected or high-level access machinery will be used at one side of each building. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Pendle College accommodation:
House 21 Ullswater - starting in February - end of February
House 24 Winewall - 12 January - end of February
House 27 Crowtrees - 12 January - end of February
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Lonsdale College accommodation:
House 40 Casterton - works have started and will continue until late February 2026
House 43 Arkholme -works will start 16 February and will continue until end of March 2026
- Scaffolding will be erected or high-level access machinery will be used at one side of each house. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.
- Dates can be subject to change.