The University and the Net Zero Energy Project contractor, Vital Energi, have programmed the following work to reduce disruption to our campus community as far as possible. We apologise for any disruption the work may cause you.
Last updated: Friday 5 June 2026.
Programme of works
The Net Zero Energy Project includes three elements of work. Further details, including current and upcoming works and how they may affect you, can be found below.
November 2024 - Early 2027: Construction of a new energy centre on the outer edge of south east campus.
District Heat Network
November 2024 - December 2025: Expansion of the District Heat Network.
Building Connections
June 2025 - November 2026: Connecting buildings to the expanded District Heat Network, which will be fed by the new Energy Centre 2. This work will involve fixing district heating pipework to the facade of buildings and bringing the pipework into plant rooms and kitchens. Internal upgrades will also take place, including the replacement of existing gas boilers with new, more efficient systems.
North Campus
North Campus accordion
Until early June 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the replacement of the existing boilers with a district heating pipework connection from the Bowland Main plant room into the Welcome Centre rooftop plant room.
Work will progress between 8am – 5pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
Dates can be subject to change.
South Campus
South Campus accordion
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Fylde College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 68 Lytham
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Commissioning of the new district heating system in plant room: 29 June – 30 June 2026
House 69 Pilling
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Commissioning of the new district heating system in plant room: 1 July – 2 July 2026
How will this work affect you?
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8am – 6pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
From Thursday 18 June to late August 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the replacement of the boilers and new pipework connections in the InfoLab21 plant room.
Vital Energi contractors will be accessing the plant room externally and won’t require internal access to the building.
Work will take place between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
Dates can be subject to change.
From Monday 30 March to June 2026, the Net Zero Energy Project contractor, Vital Energi, will be installing new pipework on the north side of Energy Centre One to enable new district heating connections into the building.
Work will progress between 8am - 6pm. The project webpages list alternative study spaces if required.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Grizedale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
Houses 107-111
Installation of external pipework to the facade of the building: complete
Houses 112-113
Replacement of boilers and pipework connections in plant room: 29 June – mid-August 2026
Hot water interruption: 6 July 2026
Houses 114-115
Replacement of boilers and pipework connections in plant room: 22 July – mid-September 2026
Hot water interruption: 29 July 2026
House 116
Replacement of boilers and pipework connections in plant room: 14 August – early October 2026
Hot water interruption: 21 August 2026
Houses 117-120
Scaffolding remains in place for access purposes
Houses 121-124
Scaffolding remains in place for access purposes
Houses 125-129
Scaffolding remains in place for access purposes
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Scaffolding is in place to allow Vital Energi contractors to access plant rooms. They won't need access to any student flats.
Some pedestrian access routes in the local area are closed. Diversion signage is in place and building entrances will be maintained at all times.
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
A one-way system is in place northbound along South Drive from the LENS building up to George Fox Avenue to enable the contractor to construct the new energy centre. This one-way system will be in place until the project completes in Spring 2027.
A new entrance has been created from George Fox Avenue into George Fox car park and a contractor's compound has been created on the east side of the main car park. The west side of George Fox car park will remain in use for staff parking using the new entrance/exit from George Fox Avenue.
Alexandra Park
Alexandra Park accordion
Cartmel College Houses
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Cartmel College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 46 Bigland
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 29 June – late August 2026
Hot water interruption: 9 July 2026 (also affects Houses 47 to 49)
House 52 Haverthwaite
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 27 July – late September 2026
Hot water interruption: 6 August 2026 (also affects Houses 50 to 51)
House 54 Grange
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 2 September – early November 2026
Hot water interruption: 11 September 2026 (also affects House 53)
House 55 Braystones Tarn
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 29 June – late August 2026
Hot water interruption: 2 October 2026 (also affects House 56)
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access the plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Cartmel College Family Flats and Houses
From 7 April until early May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the external district heating pipework to Graduate College - Cartmel family flats and houses. Vital Energi contractors will be installing external pipework only at this time, in readiness for summer internal connections.
Houses 158 – 162 Lyth
External pipework installation: complete
Houses 163 – 168 Backbarrow
External pipework installation: complete
Houses 169 – 171 Hayeswater
External pipework installation: complete
Houses 172 – 179 Seathwaite
External pipework installation: complete
How will this affect you?
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
Work will progress between 8am – 6pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Graduate College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 7 Crummock Water
External pipework installation to the facade of the building: complete
House 8 Derwentwater
External pipework installation to the facade of the building: complete
Core hole drilling: complete
Internal pipework installation: complete
House 9 Devoke
External pipework installation to the facade of the building: complete
Core hole drilling: complete
Internal pipework installation: complete
House 11 Ennerdale
External pipework installation to the facade of the building: complete
Internal pipework installation: complete
House 16 Loweswater
Replacement of boilers and pipework connections in plant room: 1 September – early November 2026
Hot water interruption: 26 August 2026 (also affects Houses 12 to 15)
House 19 Stickle
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 30 July – mid-August 2026
Hot water interruption: complete
House 20 Thirlmere
Replacement of boilers and pipework connections in plant room: 6 May – 10 September 2026
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Hot water interruption: complete
House 21 Ullswater
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 4 June – 15 July 2026
Hot water interruption: 18 June 2026 (also affects Houses 22 and 23)
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Between Monday 18 May and Friday 3 July 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out pressure testing and flushing of the district heating pipework at Grizedale College accommodation, House 30 Easdale Tarn.
Vital Energi contractors will be accessing the communal stairwells but won't need access to any student flats.
Work will progress between 8am – 6pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Lonsdale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 32 Cantsfield
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 10 August – late August 2026
House 34 Whittington
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 29 June – early September 2026
Hot water interruption: 16 July 2026
House 35 Beckfoot
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 24 August – mid-September 2026
House 36 Tunstall
Replacement of boilers and pipework connections in plant room: 13 May – early September 2026
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Hot water interruption: 4 June 2026
House 37 Wennington
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 22 September – mid-October 2026
House 39 Barbon
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 27 July – early October 2026
Hot water interruption: 29 July 2026
House 40 Casterton
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 16 July – mid-September 2026
Hot water interruption: 30 July 2026 (also affects Houses 41 and 42)
House 43 Arkholme
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 13 August – mid-October 2026
Hot water interruption: 27 August 2026 (also affects Houses 44 and 45)
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Pendle College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 24 Winewall
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 18 June – mid-August 2026
Hot water interruption: 2 July 2026 (also affects Houses 25 and 26)
House 27 Crowtrees
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: 16 July – late September 2026
Hot water interruption: 6 August 2026 (also affects House 28)
House 29 Barnoldswick
Pressure testing and flushing of pipework in plant room: between 18 May – 3 July 2026
Replacement of boilers and pipework connections in plant room: complete
Hot water interruption: complete
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.