The University and the Net Zero Energy Project contractor, Vital Energi, have programmed the following work to reduce disruption to our campus community as far as possible. We apologise for any disruption the work may cause you.
Last updated: Thursday 5 November 2026.
Programme of works
The Net Zero Energy Project includes three elements of work. Further details, including current and upcoming works and how they may affect you, can be found below.
November 2024 - Early 2027: Construction of a new energy centre on the outer edge of south east campus.
District Heat Network
November 2024 - December 2025: Expansion of the District Heat Network.
Building Connections
June 2025 - November 2026: Connecting buildings to the expanded District Heat Network, which will be fed by the new Energy Centre 2. This work will involve fixing district heating pipework to the facade of buildings and bringing the pipework into plant rooms and kitchens. Internal upgrades will also take place, including the replacement of existing gas boilers with new, more efficient systems.
Campus wide
Campus wide accordion
From Monday 14 September to the end of October 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out minor leak repairs to the campus district heating pipework.
Work will take place at the following locations:
To the west of Lancaster Square (from September onwards)
Grizedale College Quad outside House 114-115 (from September onwards)
The corner of Barker House Avenue to the rear of Barker House Farm on Alexandra Park (from October onwards)
How will this affect you?
Minor excavations will be carried out to access and repair the buried pipework, causing some localised disruption. Access routes will be maintained and deliveries to the rear of Barker House Farm will not be affected.
The works are expected to take approximately three to four days to complete at each location.
Dates can be subject to change.
Until the end of January 2027, the Net Zero Energy Project contractor, Vital Energi, will be carrying out works to enclose the newly installed external district heating pipework and valves on the facade of buildings. Work will take place at:
Bowland Main
Cartmel College
County College, including County Field and County South
Furness College
Fylde College
Graduate College
Grizedale College
Lonsdale College
Pendle College
How will this affect you?
Vital Energi contractors will be working outside each building to install protective covers around the pipework and valves.
There will be short periods of drilling noise while the covers are fixed to the external wall of each building.
Work will progress between 8am – 6pm (Monday to Friday).
Dates can be subject to change.
North Campus
North Campus accordion
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the County Field residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 78 Sloe
No works scheduled at this time.
House 79 Damson
No works scheduled at this time.
House 80 Hawthorn
No works scheduled at this time.
House 91 Primrose
No works scheduled at this time.
House 92 Orchid
No works scheduled at this time.
House 93 Nettle
No works scheduled at this time.
House 94 Mallow
No works scheduled at this time.
House 101 Aconite
No works scheduled at this time.
House 106 Foxglove
No works scheduled at this time.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of House 75 Anglezarke, County South to the campus District Heat Network. There are no works scheduled at this time.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the County Main Family Flats to the campus District Heat Network. This will involve internal and external works at the following flats.
Flat 17
No works scheduled at this time.
Flat 18
No works scheduled at this time.
Flat 19
No works scheduled at this time.
Flat 20
No works scheduled at this time.
Flat 21
No works scheduled at this time.
Flat 22
No works scheduled at this time.
Flat 23
No works scheduled at this time.
Flat 24
No works scheduled at this time.
Flat 25
No works scheduled at this time.
Flat 26
No works scheduled at this time.
Flat 27
No works scheduled at this time.
South Campus
South Campus accordion
A road closure will be in place along South Drive on Saturday 7 November from 9am – 3pm to allow tarmac repair works to take place as part of the Net Zero Energy Project.
The closure will stretch from the pedestrian crossing outside Pendle Accommodation up to the east roundabout. A diversion will be in place throughout the works and will be clearly signposted.
The following travel and access changes will also be in place:
Parking bays along South Drive will be closed off on the evening of Friday 6 November.
Traffic lights will be in place at the Alexandra Park Drive junction.
The pedestrian crossing adjacent to Pendle Avenue will be out of use and traffic management operatives will be on site to marshal pedestrians. The pedestrian crossing outside Pendle accommodation will remain in use.
Furness Avenue and George Fox Avenue leading to Fylde Avenue will not be accessible. Tower Avenue will remain accessible from North Drive for deliveries only. Any vehicles left on this side of campus will be able to exit and will be supported by the traffic management team on the day where necessary.
The InfoLab21 and Furness College bus stops will be closed. Bus routes will be diverted past the Management School. Bus users should use the Underpass as an alternative bus stop.
Work will progress between 8am – 6pm and will be noisy at times. The project webpages list alternative study spaces if required.
From Monday 30 March to September 2026, the Net Zero Energy Project contractor, Vital Energi, will be installing new pipework on the north side of Energy Centre One to enable new district heating connections into the building.
Work will progress between 8am – 6pm (Monday to Friday).
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Grizedale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 107 Sawrey
Removal of scaffolding: 21 October – 23 October 2026
House 108 Tarn Hows
Removal of scaffolding: 21 October – 23 October 2026
House 109 Finsthwaite
Removal of scaffolding: 21 October – 23 October 2026
House 110 Brathay
Removal of scaffolding: 21 October – 23 October 2026
House 111 Tilberthwaite
Removal of scaffolding: 21 October – 23 October 2026
Houses 112-113 Skelwith and High Cross
Removal of scaffolding: 26 October – 28 October 2026
Houses 114-115 Sunnybank and Carron Crag
Removal of scaffolding: 28 October – 30 October 2026
House 116 Nibthwaite
Removal of scaffolding: 2 November – 4 November 2026
House 117 Townen
No works scheduled at this time.
House 118 Satterthwaite
No works scheduled at this time.
House 119 Bessy Bank
No works scheduled at this time.
House 120 Force Forge
No works scheduled at this time.
House 121 Blawith
No works scheduled at this time.
House 122 Graythwaite
No works scheduled at this time.
House 123 Newby
No works scheduled at this time.
House 124 Rusland
No works scheduled at this time.
House 125 Whinfell
No works scheduled at this time.
House 126 Storrs
No works scheduled at this time.
House 127 Sweetenthwaite
No works scheduled at this time.
House 128 Lowick
No works scheduled at this time.
House 129 Brow Edge
No works scheduled at this time.
How will this affect you?
Pedestrian diversion routes will be in place and clearly signed.
Parking spaces on South Drive will be closed off on the evening of Tuesday 27 October and will reopen as soon as the work completes.
Accessible parking spaces on Grizedale Avenue will be closed off during the works and will reopen as soon as the work completes. Alternative accessible parking is available on South Drive.
The secure cycle stores and bin stores on Grizedale Avenue will remain open.
Work will progress between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Furness College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
The remaining installation and remedial works are programmed for completion by early November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
House 71 Pennington
Installation of drainage pipework connection in plant room: 6 November 2026
House 72 Colton
Installation of drainage pipework connection in plant room: 9 November 2026
House 74 Hawkshead
Installation of drainage pipework connection in plant room: 2 November 2026
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access the plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Fylde College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
The remaining installation and remedial works are programmed for completion by mid November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
House 68 Lytham
Installation of drainage pipework connection in plant room: 11 November 2026
House 69 Pilling
No works scheduled at this time.
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access the plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
A one-way system is in place northbound along South Drive from the LENS building up to George Fox Avenue to enable the contractor to construct the new energy centre. This one-way system will be in place until the project completes in Spring 2027.
A new entrance has been created from George Fox Avenue into George Fox car park and a contractor's compound has been created on the east side of the main car park. The west side of George Fox car park will remain in use for staff parking using the new entrance/exit from George Fox Avenue.
Alexandra Park
Alexandra Park accordion
From Thursday 27 August – late November 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of new heating and hot water systems and pipework connections at Barker House Farm. Work will take place in the following areas:
Kitchen Store – Hot water storage tank replacement: works taking place until mid-November 2026
There will be no hot water for eight hours between 10pm and 6am on 3 September.
A temporary boiler will be installed to maintain hot water to the bar kitchen from 3 September to 9 September.
Storage tank replacement will take place from 10 September to 16 September.
The temporary boiler will be removed once the works are completed.
Bar Area – Hot water storage tank replacement: works taking place until mid-November 2026
There will be no hot water for eight hours between 10pm and 6am on 27 August.
A temporary boiler will be installed to maintain hot water to the bar area from 3 September to 9 September.
Storage tank replacement will take place from 10 September to 16 September.
The temporary boiler will be removed once the works are completed.
Builders work will be carried out on the external wall of the building to allow the pipework to be connected into the bar area. Once works start, there will be noise for up to 2 hours. This work will take place from 10 September to 11 September.
Plant room – Boiler replacement: works taking place until late November 2026
Temporary heating will be in place within the social, study and dining spaces as required to maintain temperature from 1 October should it be required.
Replacement of the existing boiler with a new heating and hot water system: completion by mid-November.
Commissioning of the new heating and hot water system and boiler removal: completion by end of November.
WC – Boiler replacement: 11 September to 15 September 2026
Replacement of the existing boiler with a new heating and hot water system and pipework connections into the building from 11 September to 15 September.
There will be cold water feed only to the WC during these works.
Work will take place between 8.30am – 5.30pm (Monday to Friday), with the exception of the out of hours working noted above. The work will be noisy at times. The project webpages list alternative study spaces if required.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Cartmel College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
The remaining installation and remedial works are programmed for completion by end of November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
House 20 Thirlmere
No works scheduled at this time.
House 46 Bigland
Installation of drainage pipework connection in plant room: 4 November 2026.
Remedial works in plant room: completion by end of November 2026.
House 52 Haverthwaite
Remedial works in plant room: completion by end of November 2026.
House 54 Grange
Commissioning of the new district heating system in plant room: 26 October – mid November 2026
Remedial works in plant room: completion by end of November 2026.
House 55 Braystones Tarn
Commissioning of the new district heating system in plant room: 26 October – mid November 2026
Remedial works in plant room: completion by end of November 2026
Houses 158 to 162 Lyth (Family Flats)
No works scheduled at this time.
Houses 163 to 168 Backbarrow (Family Flats)
No works scheduled at this time.
Houses 169 to 171 Hayeswater
No works scheduled at this time.
Houses 172 to 179 Seathwaite
No works scheduled at this time.
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access the plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Graduate College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
The remaining installation and remedial works are programmed for completion by mid November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
House 1 Bassenthwaite
No works scheduled at this time.
House 2 Blea
No works scheduled at this time.
House 3 Brotherswater
No works scheduled at this time.
House 4 Burnmoor
No works scheduled at this time.
House 5 Buttermere
No works scheduled at this time.
House 6 Coniston
No works scheduled at this time.
House 7 Crummock Water
No works scheduled at this time.
House 8 Derwentwater
No works scheduled at this time.
House 9 Devoke
No works scheduled at this time.
House 10 Elterwater
No works scheduled at this time.
House 11 Ennerdale
No works scheduled at this time.
House 16 Loweswater
Remedial works in plant room: completion by mid November 2026
House 19 Stickle
Remedial works in plant room: completion by early November 2026
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of House 30 Easdale Tarn, Grizedale College, to the campus District Heat Network. This will involve the following internal and external works.
The remaining installation and remedial works are programmed for completion by end of November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
Commissioning of the new district heating system and boiler removal in plant room: 2 November – mid November 2026
Remedial works in plant room: completion by end of November 2026
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access the plant room on the top floor of the house but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Lonsdale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
The remaining installation and remedial works are programmed for completion by end of November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
House 32 Cantsfield
No works scheduled at this time.
House 34 Whittington
Installation of drainage pipework connection in plant room: 10 November 2026
Remedial works in plant room: completion by early November 2026
House 35 Beckfoot
No works scheduled at this time.
House 36 Tunstall
No works scheduled at this time.
House 37 Wennington
No works scheduled at this time.
House 39 Barbon
Remedial works in plant room: completion by early November 2026
House 40 Casterton
Remedial works in plant room: completion by early November 2026
House 43 Arkholme
Installation of drainage pipework connection in plant room: 3 November 2026
Remedial works in plant room: completion by end of November 2026
Lonsdale House
No works scheduled at this time.
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is working on the connection of the Pendle College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
The remaining installation and remedial works are programmed for completion by end of November 2026. Further access will be required for final checks and system monitoring to ensure the installation is operating as intended and to allow any necessary adjustments to be made.
House 21 Ullswater
Remedial works in plant room: completion by early November 2026
House 24 Winewall
Installation of drainage pipework connection in plant room: 13 November 2026
Remedial works in plant room: completion by early November 2026
House 27 Crowtrees
Installation of drainage pipework connection in plant room: 12 November 2026
Remedial works in plant room: completion by early November 2026
House 29 Barnoldswick
Installation of drainage pipework connection in plant room: 5 November 2026
Remedial works in plant room: completion by end of November 2026
How will this affect you?
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Contact the Facilities Helpdesk
If you have any questions about the project and work taking place across campus you can contact the Facilities Helpdesk (Mon-Fri 9am-5pm).